PROJECT CONSTRUCTION SUMMARY

PHASE 1       Duration 7 – 8 Months

PHASE 2       Duration 18 Months

PHASE 3       Duration 9 – 10 Months

              Construction Milestones       Early Start     Late Finish
Shoring/Excavation – Bldg 2/3/4/5 May 16, 2018 January 28, 2019
Foundation and Underground – Bldg 2/3/4/5 January 28, 2019 March 31, 2020
Superstructure – Bldg 2/3/4/5 April 2, 2020 August 27, 2021
Targeted Residential Occupancy                       August 31, 2022
Shoring/Excavation – Bldg 1 September 27, 2018 January 15, 2019
Foundation and Underground- Bldg 1 January 15, 2019 March 31, 2020
Superstructure- Bldg 1 January 15, 2021 July 15, 2021
Targeted Residential Occupancy                     August 15, 2022