PROJECT CONSTRUCTION SUMMARY
PHASE 1 Duration 7 – 8 Months
- Abatement and Site Preparation Including Steel Reinforcement of Heritage Corner Building Facades
- Non-Heritage Demolition
- Heritage Demolition
- Shoring
- Excavation
PHASE 2 Duration 18 Months
- Footings & Foundation
- Waterproofing
- Neighbourhood Energy System (NES) Central Plant Work
- Glazing Start
PHASE 3 Duration 9 – 10 Months
- Above-Grade Construction (Level 4+)
- Precast
- Glass
- Interior Works
- Park
- Landscape
- Market
Construction Milestones | Early Start | Late Finish |
Shoring/Excavation – Bldg 2/3/4/5 | May 16, 2018 | January 28, 2019 |
Foundation and Underground – Bldg 2/3/4/5 | January 28, 2019 | March 31, 2020 |
Superstructure – Bldg 2/3/4/5 | April 2, 2020 | August 27, 2021 |
Targeted Residential Occupancy | August 31, 2022 | |
Shoring/Excavation – Bldg 1 | September 27, 2018 | January 15, 2019 |
Foundation and Underground- Bldg 1 | January 15, 2019 | March 31, 2020 |
Superstructure- Bldg 1 | January 15, 2021 | July 15, 2021 |
Targeted Residential Occupancy | August 15, 2022 |